Causeway Kaki
Home / Live checks / RTS Link opening date

RTS Link opening date and fare

What is confirmed, what is a target, and what is only a guess about the Woodlands North to Bukit Chagar line.

Status

The RTS Link is not running yet, so there is no live number for it. For what is running today, open the live crossing status.

Checked: facts on this page were last verified against LTA sources on 8 September 2026 (see our RTS Link guide). Nothing has been added since.

The short answer on the opening date

There is no fixed date you can plan a trip around. LTA's own project page states a target of the end of 2026. Singapore's Parliament referred to December 2026 during the May 2026 reading of the Cross-Border Railways Bill. Reporting around the 4 September 2026 completion of the Woodlands North station structure describes passenger service as slated for 2027 while systems testing continues. The honest reading across those three is that the line is close, but close means around the turn of 2026 into 2027, and any specific day you see quoted is provisional until both governments announce a launch.

The fare

There is no official fare. The proposed fare structure was still due to be submitted to both governments for approval, and until one is approved and published, any figure is an estimate. Numbers of roughly S$5 to S$7 one way appear on third-party sites, but those are unconfirmed projections, and we will not state a fare as fact until an official one exists.

What the RTS Link is

It is a 4 km cross-border rail line between Woodlands North station in Singapore and Bukit Chagar station in Johor Bahru, with a journey of about five minutes. It is designed to carry up to 10,000 passengers an hour in each direction. Immigration for both countries is done together at the departure station before you board, so there is no road queue to sit in. On the Singapore side it connects to the Thomson-East Coast Line.

What to do until it opens

Nothing changes for the crossing you use today. Buses, the KTM shuttle, taxis and driving all carry on as they are. Plan around what is live now, and treat the RTS as something to switch to once it is genuinely open. To see current conditions at the checkpoints, use the live Woodlands and Tuas checks. Our full RTS Link guide has more, and the KTM Shuttle guide covers the current rail option.

How we get this number

Facts come from the Land Transport Authority's RTS Link project page, cross-checked against LTA's 4 September 2026 announcement that the Woodlands North station structure is complete, and Singapore Parliament's May 2026 reading of the Cross-Border Railways Bill. There is no live data for a line that is not yet running.

Page last built 2026-11-22.

Frequently asked questions

When does the RTS Link open?

No firm date is confirmed. LTA targets the end of 2026, Parliament mentioned December 2026, and reports around September 2026 point to passenger service in 2027.

How much will the RTS Link fare be?

There is no official fare yet. Figures of around S$5 to S$7 are unconfirmed third-party estimates.

Will it replace the Causeway?

No. It gives rail and foot passengers a route that skips the road queue. Cars, buses and fuel check rules continue as they are.